Construction Update - May

9fad3b5d-5858-471f-bdca-dd847c4233fe.jpg

Internal fit out is well progressed with concrete flooring complete and polishing to occur in the coming month.  

Service trades are finishing works and moving into the commissioning phase of the project. 

External works are taking shape with the commencement of planting around the central carpark and northern access road. 

Night works may occur over the next few months, depending on the weather conditions and how it affects the work schedule. During these periods, people nearby may notice the car park lights on at night as a temporary measure.